One, Mobile installation:

Between the floor and the floor with the manufacturer's special connection with the adhesive into one, the floor and the floor is not adhered to, you can arbitrarily move the PVC movement of the floor roll up or move away, easy to move.

Second, fixed installation:

1. Semi-stationary: special double-sided tape, the floor and the floor with the manufacturer of special double-sided tape belt adhesive into one, while the floor and the ground is also connected to the bonding, can effectively prevent the floor due to the strenuous movement of movement, open seam, but also facilitate the future because of the need to do the whole site move.

2. Local bonding: On the ground to the edge of the floor as the benchmark to the internal brush 20cm adhesive bonding.

3. Full adhesive Bonding: In the upcoming laying of all the surface of the brush adhesive bonding.

"Grassroots Requirements":

Construction ground base must be clean, durable clean, high flatness, and no cracks. The water content of concrete surface can not exceed 2.5%. The water content of gypsum surface shall not exceed 0.5%. Floor before laying. After dust removal, the flooring can be laid on PVC sports floor. If the original ground uneven can also be constructed around 2mm of self-leveling. If it is not absorbent ground such as mineral base, stone, tile, etc., direct paving can be.

"Note": If the basement is wet, the floor must be waterproof to isolate the water vapor.

Install steps:

1. Laying the ground must be flat and clean.

2.PVC moving floor before laying, it is necessary to spread the tile in advance for more than 24 hours, and the site temperature should not be less than 15 ℃. When the floor is restored, the two ends of the cutting should remain 5cm. Before pasting, will expand the floor reverse roll up about half, then scrape the glue to lay-starts from the middle-glue uses the toothed scraper to carry on the construction.

3. According to the number sequence of floors, alignment combined, pay attention to the paving process to align the site line.

4. Open two adjacent floors along the joint, manufacturers supporting the use of a dedicated connection to the next side of the joint, in the connection with the surface of the brush, the first one of the plate to adhere to the half of the belt, and then the other half glued to the remaining connection belt, the gap can be tight.

5. It is recommended to use water soluble glue to construct harmless human body. Floor paste with cork block from the middle to both ends of the floor to squeeze the surface of the flat without bubble, the most complete rolling formation.

6. After the floor is glued to the groove, welding, after welding to the welding line leveled.

interlocking-pvc-floor-tiles.jpg

  • Colorful Vinyl Flooring
  • PVC Wood Flooring
  • Vinyl Plank Flooring
  • Homogeneous Vinyl Flooring
  • Transport Flooring
  • Black PVC Laminate Flooring

Related Products